Earned Value Management[EVM]
- EVM is used in planning, management and control of projects and programs
- It is a project management budgeting technique measuring cost and schedule against a baseline
- The result is a simple set of metrics that provide early warnings of performance issues and allows for timely and appropriate adjustments to be made
Earned Value Equations
-
Total budget cost for the project OR Budget at completion (BAC)
- Original budget of the project
BAC = Given
- Original budget of the project
-
Planned Value (PV)
- This is the budgeted cost of work that is scheduled to be done at a given point in time
- This is the amount of money worth of work that should have been done till now
PV = Budgeted Cost of work X Planned completion
-
Earned Value (EV)
- Budgeted cost of work which is actually performed at any given point of time
- Amount of money worth of work that has actually been done on the project
EV = Budgeted cost of work X Actual % Complete
-
Actual Cost (AC)
- This is the actual cost that is incurred for all of the work that is performed at any given point of time
- money spent on the project so far
**AC = Given **
-
Cost variance (CV)
- Difference between actual work done and money spent
- Difference between earned value and actual cost
- Negative value means we are over budget
CV = EV - AC
-
Cost Performance Index (CPI)
- Rate of how we are spending to actually earning on the project
- Measure of cost efficiency
- Value under 1 means we are over budget
CPI = EV / AC
-
Schedule Variance (SV)
- Difference between the amount of work done against the amount of work that should have been done
- Difference between earned value and the planned value
- Negative value means we are behind schedule
SV = EV - PV
-
Schedule Performance Index (SPI)
- Rate of how we are meeting project schedule
- Measure of schedule efficiency
- Value under 1 means we are behind schedule
SPI = EV / PV
-
Estimate at Completion (EAC)
- Forecasting the total value cost of the project at the end based on the current rate of spending
EAC = BAC / CPI
- Forecasting the total value cost of the project at the end based on the current rate of spending
-
Estimate to complete (ETC)
- Forecasting the amount that will be needed to complete the current project based on the current performance
ETC = EAC - AC
- Forecasting the amount that will be needed to complete the current project based on the current performance
-
Variance at completion (VAC)
- Difference between original budget and new forcasted budget
- If positive, it means under budget
VAC = BAC - EAC
-
To-complete Performance Index (TCPI)
- Performance that needs to be met to complete the project within the budget
- Number above 1 means team needs to work harder than currently to finish the project
TCPI = (BAC -EV) / (BAC - AC)
Scenario 1 BAC = $100 Duration 5 days PV = $60 EV = 75% X 100 = $75 AC = $70
Cost Variance (CV) = 75 - 70 = 5 (Under Budget) CPI = 1.07 Schedule Variance (SV) = 75% - 60% = 15% (Ahead of schedule) SPI = 1.25 EAC = 100 / 1.07 = 93.45 ETC = 93.45 - 70 = 23.45
VAC = 6.55 TCPI = 25/30 = 0.83
Scenario 2 BAC = $4000 Duration = 4 years = 48 months Completed = 17 months PV = 17/48 X 4000 = 1417 EV = 0.35 X 4000 = 1400 AC = 1500 CV = -100 Over budget CPI = 1400/15000 = 0.93 Over budget SV = 1400 - 1417 = -17 behind schedule SPI = 1400/1417 = 0.98 = behind schedule EAC = 4000/0.93 = 4301 ETC = 2801 VAC = -301 TCPI = 1.04