Project Documents

S. No. Phase Process Project Document Description
1 Initiation Develop project Charter Assumption Log List of all project assumptions and constraints
2 Identify Stakeholders Stakeholder Register List of all stakeholders, which can include categorisation, impact and communication requirements
3 Planning Develop project Management Plan
4 Plan Scope Management
5 Collect Requirements Requirements Traceability Matrix A table that traces the origin of the requirements.
6 Requirements Documentation Description of all requirements from project stakeholders
7 Define Scope Project Scope Statement A detailed description of the project or phase deliverables
8 Create WBS
9 Plan Schedule Management
10 Define Activities Activity List List of all activities in the project
11 Milestone List Descriptions of milestones on the project
12 Activity Attributes Detailed information about each individual activity
13 Sequence Activities Project Schedule Network Diagram A sequencing diagram that shows relationships amongst the project activities and the sequence they will be performed. Also shows Critical Path
14 Estimate Activity Duration Duration Estimates Amount of time needed to complete each activity on the project
15 Basis of Estimates Describes how schedule, cost and resource estimates were developed. Also includes their confidence level and ranges
16 Develop Schedule Project Schedule A detailed breakdown of work that needs to be done in order to complete the project. Could include a bar chart, milestone chart and the project schedule network diagram
17 Schedule data The information that is used to create the schedule such as who made it, assumptions and constraints
18 Project Calendars A calendar view of what takes place on a day-to-day basis on the project
19 Plan Cost Management
20 Estimate Costs Cost estimates Cost of each individual activity
21 Basis of Estimates Describes how schedule, cost and resource estimates were developed. Also includes their confidence level and ranges
22 Determine Budget
23 Plan quality management Quality Metrics An attribute that will be used to measure the project or deliverable to verify that it has met the quality requirements
24 Plan resource management Team Charter Guidelines that team should follow on a project. Includes values, decision-making process, acceptable behaviour, code of conduct
25 Estimate Activity resources Resource Breakdown Structure Categorization and type of the project resources
26 Resource Requirements Description of the number and type of resources needed to complete each work package or activity
27 Basis of Estimates Describes how schedule, cost and resource estimates were developed. Also includes their confidence level and ranges
28 Plan Communication Management
29 Plan Risk Management
30 Identify Risks Risk Register A list of all positive and negative risks on a project, along with responses.
31 Risk Report A description of the overall project risks.
32 Perform qualitative risk analysis
33 Perform quantitative risk analysis
34 Plan risk responses
35 Plan Procurement Management
36 Plan stakeholder engagement
37 Executing Direct and Manage Project work Issue Log List of all issues on the project
38 Manage Project knowledge Lessons Learned Register List of all lessons learned throughout the project
39 Manage quality Quality Report Generally includes information about quality issues on the project and recommendations on how to improve the processes on the project
40 Test and evaluation documents Used to help evaluate the project delivrables when completed
41 Acquire Resources Proejct team Assignments Assignment of the project team members to the work packages or activities
42 Physical Resource Assignments Assignments of the physical resources to the activities or work packages
43 Resource calendars Shows the availability of resources on the project - both physical and human resources
44 Develop team
45 Manage team
46 Manage communications Project communications Communicate in on the project by following the communications management plan
47 Implement risk response
48 Conduct procurement
49 Manage stakeholder engagement
50 Monitoring and Controlling Monitor and control product work
51 Perform integrated change control Change Log Lists and describes the status of change requests that is being processed or have been processed through the perform integrated change control process
52 Validate Scope
53 Control Scope
54 Control Schedule Schedule Forecasts A prediction of when the project may be completed based on the current progress of work
55 Control Costs Costs Forecasts Prediction of how muchthe project will cost when it completes based on current work
56 Control Quality Quality control measurements Results of the activities done in the “control quality” processes to determine if the quality standards were met
57 Control Resources
58 Monitor communications
59 Monitor Risks
60 Control procurement
61 Monitor stakeholder engagement
62 Closing Close project or phase