Predictive projects
Initiation
-
Develop Project charter
- Charter - Formally authorises the project
- Charter - Assigns the authority to the Project Manager
- Input
- Business Case
- Project Benefits Management Plan - measures benefit of the output of the project
- Agreements
- Output
- Project charter
- Assumption log
-
Identify Stakeholders
- Identify stakeholders regularly
- Record relevant information regarding their interests and involvements
- Tools
- Stakehlder analysis
- Stakeholder mapping [power Interest grid, Cube, Salience model, Directions of Influence, Prioritisation]
- Outputs
- Stakeholder register
- Contact
- Role
- Comms requirement
- Expectations
- Interest
- Influence
- Change requests
- Project Management plan updates
- Document updates
- Stakeholder register
Planning
-
Develop project management plan
- Define, prepare and coordinate all plan components
- Contains baselines and plans
- Output
- Project Management Plan
- 4 baselines
- 14 subsidiary plans
- Outlines how project is executed, monitored, controlled and closed
- Project Management Plan
-
Plan Scope Management
- How the project scope will be defined, validated and controlled
- Output
- Scope management Plan
- How scope will be defined, developed, monitored, controlled and verified
- How changes requests to the scope will be processed
- Requirements management plan
- How requirements will be analysed, documented and managed
- Traceability structure
- Scope management Plan
-
Collect Requirements
- Process of determining, collecting and documenting stakeholder needs and requirements
- Tools
- Mind mapping
- Gather ideas through brainstorming (like graph view on Obsidian or Logseq)
- Affinity diagrams
- Ideas are sorted and grouped together for further review and analysis
- Mind mapping
- Outputs
- Requirements Documentation
- Stakelholder and business requirements
- Acceptance criteria
- Quality requirements
- Porject objectives
- Impacts, Compliance
- Assumptions and constraints
- Requirements Traceability Matrix
- Once a requirement is created, a table is created to link it to its original source to help manag changes to project scope
- Requirements Documentation
-
Define Scope
- Develop a detailed description of the product and the project
- Outputs
- Project Scope statement
- Detail the project deliverable
- Project Scope statement
-
Create WBS
- WBS - Work breakdown structure
- Subdividing project deliverables and project work into smaller components
- Tools
- Decomposition
- Breaking down project deliverables into smaller components
- Decomposition
- Output
- Scope baseline
- Project scope statement
- WBS
- Each node in WBS has a number used to locate and arrange each node
- WBS Dictionary
- Details content of WBS
- Should include team member assigned, time estimate, cost estimate, account info, work package ID, milestones etc.
- Scope baseline
-
Plan Schedule Management
- Output
- Schedule Management Plan
- Levels of accuracy
- Rules of performance measurement
- Reporting formats
- Release and iteration length
- Project schedule model development
- Schedule Management Plan
- Output
-
Define activities
- Deliverables (Scope statement) → Work Packages (WBS) → Activities
- It provides a basis of estimating, scheduling, execuitng, monitoring and controlling the project work
- Tools
- Decomposition - Breaking down tasks
- Rolling wave planning
- Form of progressive elaboration
- Near term work packages are able to be defined in larger detail while long term packages may not be - they are created as place holders
- As time moves along, more details become available
- Output
- Activity list
- Activity Attributes
- Any additional information required to execute the activity list
- Milestone list - key dates of the project
-
Sequence activities
- Takes the activity list and arranges it in order they must be performed
- Tools
- Precedence Diagramming Method (PDM)
- Graphical representation of everything that needs to be done in order - shows logical relationships as well
- Dependency determination
- Mandatory (Hard logic) → A must be completed before B can start
- Discretionary (Soft logic) → A and B may or may not be performed together or in any order
- External DependencY - relationship between project and non-project activities, outside project team's control
- Internal Dependency - Team control the acitvities
- Lags and Leads
- Lead is a amount of time a successor activity can be advanced with respect to predecessor. Activity B can start even after 50% of activity A is done
- Lag directs the delay in successor activity. Activity B can start 2 days after activity A
- Precedence Diagramming Method (PDM)
- Outputs
- Project schedule network diagrams
-
Estimate activity durations
- Amount of time each activity will take to complete
- Should be done by people most familiar with the work
-
Tools
- Expert judgement
- Analogous Estimating (Top-down)
- Relies on historical info to predict estimates
- Used when limited info is present
- Least accuracy but costs less in time and money
- can be done at the beginning of the planning
- Bottom-up Estimating
- Work has to be detailed - work is broken down to lowest levels
- Highly accurate but takes long to complete
- Parametric estimation
- Uses statistical relationship between historical data and other variables
-
Three-point estimate
- Calculates an expected durationusing a weighted average of 3 - optimistic, Pessimistic, Most Likely [(O + P + 4M)/6]
PERT FORMULA = (O + P + 4M)/6
- Calculates an expected durationusing a weighted average of 3 - optimistic, Pessimistic, Most Likely [(O + P + 4M)/6]
-
Reserve Analysis
- Buffer time or contingency reserve added to combat risks
- Outputs
- Duration Estiimates - estimates of all activities
- Basis of Estimates
- How estimates were developed and their ranges
- All assumptions and constraints for creating the estimates are mentioned
-
Develop schedule
- Generate a scheudle model with planned dates
- **Tools **
- Schedule Network Analysis
- Critical Path Method
- Critical Chain Method
- What if analysis OR Monte Carlo Simulations
- Resource optimisation
- Resource optimizer Techniques (Resource Levelling)
- Method to flatten the schedule when resources are over-allocated
- Schedule compression
- Crashing (Adding resources)
- Always adds cost, may add additional risk
- Fast tracking (Activities in parallel)
- May increase risk, may or may not add cost
- Crashing (Adding resources)
- PMIS - Project Management Information System
- Agile Release planning - break into smaller iterations
- Schedule Network Analysis
- Outputs
- Project Schedule (Each activity start and end date)
- Project network diagrams
- Milestone chart
- Bar chart or Gantt chart
- Schedule baseline
- Schedule data
- Project Calendars
- Project Schedule (Each activity start and end date)
-
Plan Cost management
- Defines how the project costs will be estimated, budgeted, managed, controlled and monitored
- Provides guidance and direction on how project costs will be managed throughout the project
- Value Engineering
- Finding less costly way of doing work
- Look to achieve a goal in the least costly way
- Output
- Cost management plan
- How costs will be planned, structured and controlled
- Units of measure
- Level of accuracy
- Reporting formats
- Control thresholds
- Cost management plan
-
Estimate Costs
- Assign cost to individual activities
- Develop an approximation of the cost of resources to compleet the project
- Accuracy increases with project progression
- Definitive estimates = -5% to +10%
- Budget estimates = -10% to 25%
- Rough order of magnitude = -25% to 75%
- Tools
- Expert judgement
- Reserve Analysis
- Cost of quality
- Failure
- Success
- Output
- Cost Estimates - cost of each activity
- Basis of estimates
- Range of possible estimates
- Confidence level of estimates
- How estimates were developed and by whom
-
Determine Budget
- Tools
- Cost aggregation
- Contingency reserves
- Managed by Project Manager
- For nown/unknown risks
- Management Reserves
- Management owned
- for unknown/known risks
- Funding limit reconciliations
- Current run rate vs what was planned over the cycle of the project
- Financing
- Acquire money from external resource
- Historical Information review
- Parametric or analgous estimates based off historical projects
-
Output
-
Cost baseline
- Cost of all activities
- Typically displayed in a S-curve graph
- Represents Project cost, including contingency reserves
Project budget = Cost Baseline +Management Reserves
-
Project fundign requirements
- What gets funded when and by how much
-
- Tools
-
Plan Quality management
- Identifying quality requirements
- Documenting how the project will demonstrate complaince with quality requirements and/or standards
- Guidance and directions on how quality will be managed and verified throughout the project
- What quality specs are and how will they be met
- Tools
- Cost benefit analysis
- Cost of quality
- Test and Inspection planning
- Matrix Diagram - Relationship between two or more groups between the projects
- Mind mapping - Visually organise data
- Flowcharts - Graphical representation of the processes
- Output
- Quality management plan
- Quality standards
- Quality control
- Quality tools
- Quality Metrics
- Specs on how quality will be measured
- Quality management plan
-
Plan Resource management
- How to estimate, acquire, manage and use team and physical resources
- Tools
- Organisation charts
- Hierarchical charts
- Matrix based charts (eg. RACI)
- Text oriented format
- Organisational Theory
- Organisation charts
- Output
- Resource management plan
- Will guide the remaining 5 resource management plans
- Contains roles and responsibilities, org chart and project team resource management
- Team Charter
- Outlines acceptable behaviour in the project
- General rules of conduct, decision making and one-on-one comms
- Resource management plan
-
Estimate activity resources
- Look ta each activity and their resource requirements - not just people but also other physical and non-physical resources
- Output
- Resource requirements
- Number and type of resources needed for each activity
- Resource breakdown structure
- Hierarchical breakdown of resources by their categories and types
- Basis of Estimates
- How estimates were created
- Resource requirements
-
Plan Communications Management
- Approach and plan for project communication activities
- Based on information needs of the stakeholders
-
Tools
- Expert Judgement
-
Communication requirement analysis
- Analyzing the comms needs of the stakeholders
Comms channels = n{n-1}/2
- Analyzing the comms needs of the stakeholders
-
Comms Technology
- Comms Methods
- Comms Models
- Output
- Comms Management plan
- Who should receive comms
- What comms to be received
- Who will send it
- How will it be sent
- How often will it be sent
-
Plan Risk Management
- Risk is only probable; Can be positive or negative
- Conduct risk management planning, identification, analysis, response planning, implementation and monitoring risk on the project
- Output
- Risk Management Plan
- How risk will be categorised
- How analysis will be completed
- How risk responses will be implemented
- How risk will be monitored
- How ongoing risk management activities will happen throughout the project
- Risk Management Plan
-
Identify Risks
- Idenitify individual project risks as well as sources of overall project risks
- Document in risk register and risk report
- Identify both positive and negative risks
- Tools
- Prompt list - predetermined list of risk categories
- Output
- Risk Register - usually Project manager deals with it
- List of all identified risks
- list of potential responses
- Risk report - Usually the org deals with this
- Sources of overall project risks and summary info on identified individual risks
- Risk Register - usually Project manager deals with it
-
Perform Qualitative Risk analysis
- Prioritise individual risk by assessing their probablility of occurence and impact
- Create a ranking
- Done throughout the project
- Tools
- Risk Probablility and Impact assessment
- Risk data quality assessment
- Risk Categorisation (Grouped by root cause)
- Risk bubble chart
- Risk Impact matrix
- Output
- Risk register
- Ranking of the risks
- Risk Report
- Risk register
-
Perform Quantitaitve Risk analysis
- Numerically analysing the effect of individual project risk on overall project deliverables
- Requires specific risk software and knowledge in development and interpretation of risk models
- Tools
- Respresentation of uncertainity
- Triangular or beta distributions
- Probability distributions
- Sensitivity analysis
- Tornado chart
- Decision Tree Analysis (Make or buy analysis as an example)
- Respresentation of uncertainity
- Output
- Risk Register
- Values to each risk
- Risk Register
-
Plan Risk responses
- Developing options, selecting strategies on ways to address risk on the project
- Tools
- Strategies for negative risks [$]
- Escalate
- Avoid
- Transfer
- Mitigate
- Accept
- Strategies for positive risks [$]
- Escalate
- Exploit
- Share
- Enhance
- Accept
- Contingent Response strategies
- May understake certain risk events
- Strategies for negative risks [$]
- Outputs
- Risk Register
- Risk responses
- Risk Register
-
Plan Procurement Management
- Determine whether to obtain goods and services from outside the project
- Tools
- Source Selection Analysis
- Outputs
- Procurement Management Plan
- Outlines activities to be taken during procurement processes
- Procurement Strategy
- Type of contracts to use
- Bid documents
- Used to solicit proposals
- Procurement Statement of work
- Developed from the scope baseline, lists the needs of the buyer
- Source Selection criteria
- make or buy decisions
- Independent cost estimates
- Change requests
- Procurement Management Plan
-
Plan Stakeholder Engagement
- methods to involve stakeholders
- Centered on their needs, expectations, interests and potential impact
- Tools
- Stakeholder engagement assessment matrix
- 5 levels of engagement
- Unaware
- Resistant
- Neutral
- Supportive
- Leading
- 5 levels of engagement
- Stakeholder engagement assessment matrix
- Output
- Stakeholder management plan (works with communication management plan)
- How will we keep them engaged
- Communication needed to keep them engaged
- Stakeholder management plan (works with communication management plan)
Executing
-
Direct and Manage project work
- This is an integration process that encompasses all the processes in this section (execution)
- Performing the work defined in the project management plan
- Output
- Deliverables - any product, service or result required to complete the project
- Work Performance Data
- Information on status of deliverables
- Is it tracking +/- against the baseline
- Issue Log
- Record of all problems encountered on the project
- Change Request
-
Manage project Knowledge
- Update existing knowledge and create new knowledge
- Knowledge created is either Explicit or Tacit
- Explicit - can be formally documented and shared (Data, Document, Records)
- Tacit - exists inside heads of the employees (Experience, Thinking)
- Tools
- Knowledge Management
- Sharing of knowledge between stakeholders of the project
- Information Management
- Collection, Storage, dissemination, archiving and destruction of information
- Knowledge Management
- Output
- Lesson Learned Register
- Gathered throughout the project and not just at the end
- Lesson Learned Register
-
Manage Quality
- Quality Assurance
- Translating the quality management plan into executable quality activities
- Tools
- Affinity Diagrams
- Matrix Diagrams
- Cause and Effect DIagrams
- Ishikawa or Fishbone Diagrams
- Tells the main causes of defects
- Flowcharts
- Histograms
- Pareto Chart/Diagram - Uses Pareto priniciple of 80/20 - 80% of project problems or defects come from 20% of causes
- Scatter Diagram
- Quality Audits
- Idenitfy all best practices are being used
- Design for X
- Used by engineers in order to design a particular aspect of a product
- Problem Solving
- Quality Improvement Methods
- Output
- Quality Reports
- Information about quality issues on the project
- Recommendations on how to improve the processes being used
- Test and Evaluation Documents
- Checklist to be used when checking the deliverable quality
- Quality Reports
-
Acquire Resources
- Getting staff and physical resources needed
- Done continuously through the project
- Both internal and external resources
- Tools
- Decision Making
- Multi-criteria decision analysis (Multiple criterias are used for decision making)
- Pre-assignment
- Team members are selected in advance of the project
- Virtual Teams
- Decision Making
- Outputs
- Physical resource assignments
- How to allocate physical resources on the project
- Project Team Assignments
- Assign the team to their roles and responsibilities
- Resource Calendar
- Shows availability of the resources
- Physical resource assignments
-
Develop Team
- Improving team abilities, team communication and atmosphere
- Tuckman's Ladder (Five Stages)
- Forming - people getting to know each other
- Storming - Speaking about issues on project
- Norming - Coming to solution about issues
- Perfroming - Doing work
- Adjourning - Team released
- Tools
- Co-location
- Moving entire team into one physical location (War room)
- Comms Technology
- Individual and Team Assessments
- Individual strengths and weaknesses
- How does team make decisions, resolve conflicts
- Recognition and rewards
- Maslow's hierarchy of needs
- Physiological
- Safety
- Social
- Esteem
- Self-actualisation
- Herzberg's theory of motivation
- Hygeine agents are expected and can lead to demotivation if not present
- Motivating agents provide opportunity to advance and excel
- McGregor's theory of X and Y
- Theory X is bad - People need to be watched all the time, micromanaged etc
- Theory Y is good - people are self-motivated
- Theory Z
- Well being of the employees, bith at work and outside, encourages steady employment
- Expectancy theory
- People behave based on what they expect as a result of their behaviour
- McClelland 3 need theory (People are motivated by following 3 things)
- Achievement
- Power
- Affiliation
- Forms of power
- Reward power - ability to give rewards
- Expert Power - SME
- Legitimate - Formal power
- Referent - Respect / Personality of the manager
- Punishment
- Punish associates when they fail
- Maslow's hierarchy of needs
- Co-location
- Outputs
- Team Performance Assessments
-
Oscar model - A situational leadership model about coaching or leadership styles to support individuals
- Outcome
- Situation
- Choices/Consequences
- Actions
- Review
-
Drexler Sibbet Team Model
- Team performance model with 7 steps
- Step 1 - orientation - Why?
- Step 2 - Trust building - Who?
- Step 3 Goal clarification - What?
- Step 4 - Commitment - how, define the plan
- Step 5 - Implementation - start working
- Step 6 - High performance - Reach a high level
- Step 7 - Renewal - Working through changes
- Step 1 to 4 is about creating the team. Step 5 to 7 is about sustainability and performance
- Team performance model with 7 steps
-
Manage Team
- Tools
- Interpersonal and Team Skills
- Conflict Management
- Problem solving
- Forcing - Win-Lose
- Compromising - Lose-Lose
- Smoothing - Lose-Lose
- Withdrawal - Yield-Lose
- Steps to follow
- Define the cause of the problem
- Analyze the problem
- Idenitfy solutions
- Implement the selected solution
- Review the solution
- Confirm that probelm is solved
- Conflict Management
- Interpersonal and Team Skills
- Outputs
- Tools
-
Manage Communications
- Output
- Project communication
- Output
-
Implement Risk Responses
- Execute risk response plans when risk happens
- Maximise project opportunities and minimise threats
-
Conduct Procurements
- Process of obtaining a seller response, selecting a seller and awarding a contract
- Output
- Select a vendor
-
Manage Stakeholder Engagement
- Communicating and working with stakeholders to meet their needs and expectations
Monitoring and Controlling
-
Monitor and Control Project work
- Inetgration process hence encompasses all processes in this phase within it
- Process of tracking, reviewing and recording the progress according to Project management plan
- Takes all the work performance information and creates a Work performance report
- Output
- Change Request
- Work performance reports
- Status of deliverables
-
Perform integrated change control
- Review all change requests; approving changes and managing changes to deliverables, project documents and project management plan
- Communicating the decisions
- Change control board (CCB)
- Group responsible for reviewing, evaluating, deferring, approving or rejecting changes to a project and for recording and communicating such decisions
- Change identified → Change submitted to the PM → Change assessed by the PM, alternate options assessed, Impact measured → Change submitted to CCB → Result communicated → Project management plan adjusted
- Tools
- Change Control Tools
- To manage change requests, status and resulting decisions
- Update stakeholders with current information
- Change Control Tools
- Outputs
- Approved change requests
- Change Log
-
Validate scope
- Last process in this phase
- It's input is a verified deliverable → which is an output of control quality process
- This process is all about formalizing acceptance of completed project deliverables
- Tools
- Inspection
- Product review, audit or walkthrough
- Inspection
- Outputs
- Accepted deliverables
- Change requests
- Work performance information
-
Control scope
- Process of monitoring the status of the project and product scope and managing changes to the scope baseline
- Scope creep needs to be identified
- Tools
- Variance Analysis - Determining whether work performed has a degree of variance as it relates to the scope baseline
- Output
- Work performance information
- Planned vs Actual performance
- Work performance information
-
Control Schedule
- Process of monitoring the status of the project and product schedule and managing changes to the schedule baseline
- Tools
- Earned Value Management
- What-if scenarios
- Outputs
- Work performance Information
-
Control costs
- Process of monitoring the status of the project cost and managing changes to the cost baseline
- Tools
- Trend Analysis
- Reserve Analysis
- Earned Value Management
- Outputs
- Costs forecasts
- Work performance Information
-
Control quality
- assess performance and ensure that the project outputs are complete, correct and meet the customer requirements
- Tools
- Inspection
- Checklists
- Check sheets
- Statistical sampling
- Questionnaires and surveys
- Testing and Evaluations
- Cuase and effect diagrams
- Scatter diagrams
- Control charts
- Will tell if a process is in control
- Idenitfy "rule of seven" - if seven points show same tendency, then the process might be biased on one side and action can be taken - Usually in manufacturing
- Histogram
- Inspection
- Outputs
- Quality control Measurements
- Verified deliverables
-
Control resources
- How to correctly manage the physical resources
- This process does not look at HR resources
-
Monitor communications
- Ensuring the communications are meeting stakeholder requirements
-
Monitor risks
- monitoring the implementation of risk response plans
-
Control procurements
- Process of managing vendor relationships, monitoring contract performance and making changes and corrections as appropriate
- Tools
- Claims Administration
- How disputed changes can be settled when the buyer and the seller cannot reach a understanding
- Negotiation is the preferred method
- Outputs
- Closed procurements
- Buyer provides the seller with formal written notice that project is completed
- Closed procurements
- Claims Administration
-
Monitor Stakeholder Engagement
- Monitoring stakeholder relationships and engagements
Closing
- Close project or phase
- Officially closes the project
- Finalises all activities
- Making sure that all documents and deliverables are up-to-date and issues are resolved
- Confirming the delivery and the formal accpetance of deliverables by the customer
- CLosing project accounts
- Reassigning personnel
- Confirming the formal acceptance of the seller's work and finalising open claims
- Audit project success or failure
- Identify lessons learned, arcihve project information for future use by the organisation
- Transfer the project's products, services or results to the next phase or to production or operations
- Investigate and document the reasons for actions taken if the project is terminated before completion
- Outputs
- Final product, service or deliverable
- FInal report
- Summary of the project
- Success or failure verdict
- variations from the baseline