Project Status based on EVM

  • CPI and SPI:
    • CPI < 1.0 indicates that the project is running over budget.
    • CPI > 1.0 indicates that the project is running under budget.
    • CPI = 1 indicates the project is within the budget.
    • SPI > 1.0 indicates the project is ahead of schedule (earned value is greater than planned value).
    • SPI < 1.0 indicates the project is behind schedule (earned value is less than planned value).
    • SPI = 1.0 indicates the project is on schedule (earned value is equal to planned value).
  • Negative schedule variance means the project is behind schedule