Project Status based on EVM
- CPI and SPI:
- CPI < 1.0 indicates that the project is running over budget.
- CPI > 1.0 indicates that the project is running under budget.
- CPI = 1 indicates the project is within the budget.
- SPI > 1.0 indicates the project is ahead of schedule (earned value is greater than planned value).
- SPI < 1.0 indicates the project is behind schedule (earned value is less than planned value).
- SPI = 1.0 indicates the project is on schedule (earned value is equal to planned value).
- Negative schedule variance means the project is behind schedule